Program is scheduled to end February 2010.
Program started December 2001.
Program entails forcemain, water main, and sewer construction
as well as treatment facility improvements.
Program provides a sanitary sewer system for 40%
of the City previously on a septic system.
42 new pump stations constructed.
48 existing pump stations rehabilitated.
15 neighborhoods with deteriorated sewer pipes
rehabilitated using trenchless technology.
16 small water main projects completed.