Chula Vista Sewer Area 19 – Basin A
This
work consists of installing 17,875 linear feet (LF) of sanitary sewer with
approximately 44 manholes as well as service laterals.
Construction Manager: Doug
VanNote
Inspectors:
Clyde Harding, Jorge Murgado
Contractor:
Foster Marine Contractors
Designer: Keith
and Schnars
Community Outreach Contact: Mario Diaz
Estimated Completion Date: Second Quarter of 2009
Completed Improvements
- In
August, the contractor began construction on SW 17 Street from SW 29
Terrace to SW 30 Terrace.
- Once
construction on those streets is complete, the contractor anticipates to
complete SW 30 Terrace, SW 30 Avenue and SW 29 Avenue, all north of SW
17 Street.