City of Fort Lauderdale Water & Wastewater Capital Improvements
 

Flamingo Park Area 4 Basin A

This project consists of the installation of approximately 13,000 liner feet (LF) of gravity sewer with manholes, 200 LF of force main and about 2,000 LF of PVC water main.

Construction Manager:                 Pierre Marcellus
Inspector:                                       Clyde Harding
Contractor:                                     Danella
Designer:                                       Keith & Schnars
Community Outreach Contact:    Mario Diaz
Notice to Proceed:                       October 18, 2005
Estimated Completion Date       First Quarter of 2008
Percent Work Complete              100% 

·         All construction is complete.

·         All restoration is complete.

·         Currently, the contractor is waiting for certification of the project from Broward County. Once certification is received, residents will be notified.

 

Map of Flamingo Park Area 4 Basin A