Melrose Manors Area 2 West Basin B (SW)
This project
includes the installation of approximately 31,350 LF of gravity sewer with
manholes and all restoration.
Construction Manager:
Doug VanNote
Inspector:
Antonio Fernandes
Contractor:
Globetec Construction
Designer:
City of Fort Lauderdale
Community Outreach Contact:
Melissa Buckner
Notice to Proceed:
January 5, 2007
Estimated Completion Date:
Second Quarter of
2008
·
All sewer
installation is complete.
·
All roads have
been paved.
·
Currently, the
contractor is conducting testing. Once testing is complete, the project will
await certification from Broward County. The certification process can take
several weeks. When certification for the project is received, residents will be
notified.