Oakland Park Boulevard Water Transmission Main
This project
includes the installation of approximately 3,340 linear feet of 30” diameter DIP
transmission water main and connections to existing water mains. Also to be
installed is approximately 900 linear feet of 30” diameter Fusible PVC by
directional drill technique with appurtenances and all restoration.
Construction Manager:
Steve Hillberg
Inspector:
Scott Sawyer/ Scott Van Lew
Contractor:
Expertech Network Inst.
Designer: Keith & Schnars
Community Outreach Contact: Mario Diaz
Notice to Proceed: November
2, 2007
Estimated Completion Date: Fourth Quarter of
2008
Percent Work Complete
12%
Completed Improvements
·
The contractor
has installed 1,000 feet of pipe from NE 30 Place and Bayview Drive, eastbound.
The work crews are now at the point where they will begin directional drilling
under the Intracoastal Waterway.
Remaining
Improvements
·
The contractor is
waiting on permits in order to continue construction work.