River Oaks Area 6 – Basin C and E
This project consists of the
installation of about 6,730 LF of gravity sewer with manholes, 4,585 LF of water
main and all restoration.
Construction
Manager: Annachiara d’Ettore
Inspector: Vanise Ford / CMTS
Contractor: Conquest Engineering Group
Designer: Camp Dresser & McKee
Community Outreach Contact:
Mario Diaz
Notice to Proceed:
September 28, 2007
Completed Improvements
·
The contractor
installed all sewer main lines and laterals from SW 19 Avenue to SW 17 Terrace
between SW 23 Street and 24 Street.
·
All new drainage
is complete on:
- SW 18
Avenue between SW 23 Street and SW 24 Street
- SW 23
Street between SW 18 Avenue and SW 17 Terrace
- SW 17
Terrace between SW 23 Street and SW 24 Street
·
All asphalt
paving is complete on:
- SW 24
Street between SW 19 Avenue and SW 17 Avenue
- SW 18
Terrace and SW 19 Avenue between SW 23 Street and SW 24 Street
- SW 23
Street between SW 19 Avenue and SW 18 Avenue
Ongoing
Improvements
·
On SW 23 Street
between SW 18 Avenue and SW 17 Terrace, the contractor:
-
Installed all catch basins, junction boxes and drainage pipes
- Is
currently restoring this area
·
On SW 18 Avenue
between SW 24 Street and SW 23 Street, the contractor:
-
Installed all catch basins, junction boxes and drainage pipes
-
Completed limerock restoration
- Is
currently working on road restoration
·
On SW 17 Terrace
between SW 24 Street and SW 23 Street, the contractor:
-
Installed all catch basins, junction boxes and drainage pipes
·
On SW 18
Avenue between SW 23 Street and SW 20 Street, the contractor:
-
Completed the milling of existing road surface between SW 23 Street and SW
22 Street
- Is
currently placing PVC sanitary sewer pipe and service laterals. The work is
40 percent complete between SW 23 Street and SW 22 Street.