City of Fort Lauderdale Water & Wastewater Capital Improvements
 

River Run - Area 4 – Basin E Phase I

This project includes the installation of gravity sewer with manholes and a force main.

 

Construction Manager:                  Annachiara d’Ettorre
Inspector:                                      Fran Grant/CMTS
Contractor:                                    Conquest Engineering
Designer:                                       Keith & Schnars
Community Outreach Contact:       Mario Diaz
Estimated Completion Date:          Third Quarter of 2008

 

Ongoing Improvements

·         In the area of SW 28 Avenue between SW 14 Street and the end of roadway construction:

  • Manholes and sewer pipe have been installed
  • Base and sub-base road restoration is complete between SW 14 Street and SW 16 Street
  • Ductile Iron Pipe (DIP) laterals are complete to the east side
  • Current activities in this area include brick pavers restoration and completion of base and sub-base road restoration along SW 28 Avenue
  • Future work in this area includes asphalt restoration and testing

 

·         In the area of SW 29 Terrace between SW 14 Street and SW 16 Street:

  • The contractor has installed:  

§         Manholes 49, 50, 51 and 52

§         965’ of sewer pipe

§         320’ of forcemain

§         Sub Base/Limerock Base/Pavement starting on SW 17 Street for approximately 300’

§         5 single DIP laterals and 1 double DIP laterals

o        Current activities in this area include the installation of PVC sewer between SW 16 Street and SW 14 Street 

o        Future work includes:

§         Forcemain completion

§         Air Release Valve (ARV) installation

§         PVC sewer installation between manhole 50 and 33 (about 300’)

§         Manhole 33 installation

§         Restoration

Map of River Run Area 4 Basin E Phase I