"To provide a premiere utility infrastructure for the sustainable future of our community"
  
Mission | FAQ | Contact Us | Home
 
 
 
City of Fort Lauderdale Water & Wastewater Capital Improvements
 

Riverside Park Area 1 – Basin C

This project includes the installation of approximately 18,237 linear feet (LF) of gravity sewer with manholes, appurtenances and all restoration and 2,102 LF of force main and 3,481 LF of water main with appurtenances and all restoration.

 

Construction Manager:                 Chip Wilson
Inspector:                                        David Jimenez
Contractor:                                     Globetec Construction
Designer:                                       City of Fort Lauderdale
Community Outreach Contact:    Traci Pollock
Notice to Proceed:                        September 17, 2007
Estimated Completion Date:       Fourth Quarter of 2008

 

Completed Improvements

·         Sewer has been installed and completed on the following roads:

o        SW 11 Avenue

o        SW 5 Place

o        SW 12 Avenue

o        SW 9 Street

o        SW 14 Terrace

o        SW 14 Avenue

o        SW 13 Avenue

o        SW 7 Street

o        SW 15 Avenue

o        SW 5 Court

o        Grand Drive

·         Forcemain has been installed and tested.

·         Sewer lateral installation is scheduled to be completed this week on SW 15 Avenue.

·         Water main is scheduled to be installed on SW 15 Avenue this week.

·         All roads are now paved with the first ¾” construction lift (final ¾” paving will be done upon project completion).

                       Paving of SW 12 Avenue is scheduled to be completed this week.

 *Please be reminded that the swale area is the responsibility of the property owner to maintain. The contractor will only water new sod for 8 weeks and then the property owner must continue. If the sod is not watered, it will not survive.

Map of Riverside Park Area 1 Basin C