Shady Banks Area 5 – Basin C
This project
includes the installation of approximately 15,986 LF of 8" Gravity Sewer System
including, laterals and appurtenances. Installation of approximately 67
manholes, as well as the required connections to existing manhole.
Construction Manager:
Pierre Marcellus
Inspector:
Clyde Harding/CMTS
Contractor:
RicMan Construction
Designer:
Keith and Schnars
Community Outreach Contact:
Traci Pollock
Notice to Proceed:
November 26, 2007
Estimated Completion Date:
Fourth Quarter of 2008
Completed Improvements
·
All sanitary
sewer has been installed within the interior portion of the neighborhood from SW
12 Court south to SW 16 Street west from SW 14 Avenue to SW 20 Avenue.
·
Testing and
restoration will continue on:
o
SW 14 Court
between SW 15 Avenue and SW 17 Avenue
o
All streets south
of SW 14 Court including SW 15 Avenue, SW 15 Terrace, SW 16 Terrace, and SW 16
Street between SW 15 Terrace and SW 16 Terrace
Ongoing Improvements
o
Construction is
currently taking place on SW 17 Avenue from SW 12 Court to Davie Boulevard and
east along Davie Boulevard to SW 15 Avenue then south to SW 12 Court.
o
At times during
this work, the entrance to Shady Banks on SW 17 Avenue will be closed and SW 15
Avenue is utilized as an entrance and an exit from the subdivision with 2 way
traffic.
o
The construction
company will divert the two lanes of eastbound traffic to the continuous
left-turn lane (median/center lane) on
Davie Boulevard
starting from SW 19 Avenue and ending at the intersection of SW 15 Avenue. The
southern eastbound lane will remain closed to traffic during the evening hours;
the inner lane will reopen to eastbound traffic. Westbound traffic lanes will
remain unchanged throughout the progression of this phase of the project.
Restoration
·
Restoration is
complete on SW 12 Court west from SW 18 Avenue to SW 14 Avenue, SW 13 Street
between SW 18 Avenue and SW 14 Avenue, SW 14 Avenue between SW 12
Court and SW 13 Court, SW 13 Court between SW 18 Avenue and SW 17 Avenue, SW 14
Street between SW 18 Avenue and SW 15 Terrace.
·
Restoration is
complete in the area of SW 19 Avenue, SW 20 Avenue, SW 16 Street, SW 16 Court,
SW 14 Court west of SW 19 Avenue. This area tested and certified.
·
Restoration is
ongoing on SW 15 Terrace between SW 13 Court and SW 16 Street, SW 15 Avenue
between SW 13 Court and SW 16 Street, SW 13 Court between SW 15 Avenue and SW 17
Avenue, SW 16 Street between SW 15 Avenue and SW 17 Street.
*The swale area is the responsibility of the property owner to maintain.
The contractor will only maintain new sod for 8 weeks and then the property
owner must continue. If the sod is not watered, it will not survive.