The objectives of the Program and Performance Audit Report (Audit
Report) performed by Sharpton, Brunson, and Company, P.A. (SBC) were
to:
·
Determine whether sufficient management controls exist
·
Review the reliability and timeliness of financial and operating
results
·
Ascertain compliance with applicable laws, regulations, and
contracts, and
·
Provide observations and recommendations to improve performance
The observations
provided in the Audit Report indicate that the program areas
selected for review:
1.
contain sufficient management controls
2.
produce reliable and timely financial and operating results
3.
are
materially compliant with applicable laws, regulations and contracts
4.
effectively contribute to the successful execution of the Program
The WaterWorks
2011 Program Management Team, which consists of CH2M HILL and
City staff, was encouraged that the SBC review team found solid
program management practices in place. The PMT also recognizes that
the observations provide an opportunity to enhance the program’s
operations, practices, processes, and procedures. Several of the
observations provided to the team during preliminary feedback
discussions are excellent suggestions which have already been
implemented by the team including reporting improvements and Change
Control Board process improvements.
CH2M HILL contract
incentives were evaluated as part of the audit review. While there
are no incentive terms in the contract, CH2M HILL has made a
commitment to the City to deliver the program for $59.8 million (for
program management and office costs). This commitment was
documented in a letter to the City Manager on April 12, 2007. This
commitment has focused CH2M HILL on completing the Program in a
timely manner and staffing at levels appropriate to deliver the
work.
Approximately 70%
of the planned facility work and 54% of the planned pipe work has
been completed. The solid program management practices that SBC
found to be in place, together with the enhancements proposed in the
audit responses will ensure a strong finish for the program. The
program is currently on schedule to have the majority of the work
completed by 2010.
The PMT responses
to the Executive Summary observations are provided below and the
remaining observation responses are summarized in Exhibit 1. While
the team realizes the audit report has generated ideas for
enhancements, many of which were previously considered, the current
program practices represent an appropriate balance between cost and
risk. Several of the enhancements recommended by the SBS Review
Team have either been implemented or are in the process of being
implemented as noted in the responses below.
Process and
Compliance Related Observations
ES-1 – Program
allowance dollars were not derived taking a risk assessment
approach.
As noted in the
performance review report, the escalation factors for 2007 to 2009
were specifically increased to assess the risk of price escalation
(bid risk) in the future. Applying these factors resulted in a
contingency allowance of $79 million.
The adequacy of the
$79 million was evaluated by the PMT through consideration of
potential sewer area cost increases and change order funding. As
stated in Commission Memo 06-157:
The new inflation
projections equate to the $79 million allowance for inflation for
remaining projects which have an approximate value of $303 million;
or a 26% total inflationary allowance for remaining work. This
allowance is intended to address the potential for continued
extraordinary construction price increases based on recent
experiences in excess of national trends and projections. This
allowance will also be utilized to address change order costs and
scope additions over the remainder of the program.
The adequacy of the
$79 million was evaluated based on sewer area cost increases, change
orders and additional scope. At the time, the gravity sewer cost
increases were estimated based on information available; many
projects were still in design and cost increases were estimated
based on previous project trends. An evaluation of potential costs
increases at the time showed the need for additional funding of $46
million for gravity sewer projects. Of this approximately $20
million was funded from the contingency remaining prior to October
2006 when the $79 million was added to the program. Therefore, the
remaining sewer area project needs were projected at $26 million.
At the same time,
the projected need for change order funds based on 6% of
construction remaining was $27 million.
Given the
additional sewer area projections of $26 and the remaining change
order projected funding needs of $27 and accounting for additional
scope, the proposed $79 million allowance was determined to be
appropriate.
As designs have
been finalized, additional cost adjustments have been necessary,
particularly for sewer area projects. An analysis of the adequacy
of the contingency fund is provided under Observation ES-3.
ES -2 – Commission
Agenda Reports (CARs) presented to the City Commission do not
identify the cost impact of construction awards versus the Program
Controls System (PCS) budget.
The information
presented in CARs is intended to include information that is most
relevant to the recommendation being presented to the Commission.
Information regarding the program level budget; and projects that
have been added to and deleted from the program, have been reported
periodically to the Commission. It is not believed that providing
budget information on a project-by-project basis would add value
to project-level decision
making. Since the original goal was to implement all projects
identified in the Program Delivery Plan; since budget has been
managed and reported on a program level scope; and since project
scope is largely not discretionary – the individual project budget
overruns and underruns have been managed internally, with the
overall goal being to deliver as many of the projects as possible
under the existing program budget.
ES -3 – Current
contingency balance does not appear to be sufficient to complete the
program as currently scoped.
The PMT has taken
the approach that additional rate increases to fund the Program are
not feasible and that the Program should be managed to the current
budget. Projects are prioritized to provide the highest priority
projects within the budgetary constraints. Projects are proposed
for deferral to deliver the highest priority projects while keeping
the Program within budget. We agree that there is the possibility
that additional projects may need to be deferred but not to the
extent suggested by the SBC review team.
Additional details
on the contingency balance evaluation are provided in Appendix A. A
summary of the results is provided below.
Contingency Fund
Adequacy
The PMT will
continue to provide updates to the City Commission on the adequacy
of the contingency fund. The majority of the work has been bid and
awarded which has greatly reduced the remaining bid risk.
Contracted bid risk
- An analysis of the contract awards versus the PCS budget and
contingency funding projections is provided in Appendix A. This
analysis shows that the PMT has generally made adequate projections
for the anticipated budget adjustments. The average variance for
the combined budget and contingency projection versus the award
showed that the projection was 3% higher than the award on average
which indicates that the projections to date have been conservative.
With the exception of gravity sewer projects, the total projected
need was below the contract award price by 11 to 33%. However, the
gravity sewer contracts were 16% higher than planned.
Remaining bid risk
– Based on the current bid risk evaluation, the PMT believes the
projections for the remaining contract projects are adequate.
However, to take this evaluation one step further, the PMT has
assumed that an additional 20% cost increase could be incurred on
the gravity sewer projects. Under this worst-case scenario, the
program would need an additional $10 million in funding which is
well below the range of $42 to $79 million for bid risks projected
in the Audit Report.
Change orders
- Contingency fund needs for potential future change orders has been
projected based on 6% of all remaining construction budgets
(remaining active and future) and is currently estimated at $20
million. The current change order rate for completed projects is
2.2% and 3.4% for all projects – active and completed. Therefore,
based on historical program data, 6% is a conservative estimate.
Approximately $86 million will be performed by City crews or
funded from the Fiveash membrane fund. This leaves only $243
million in contract work (remaining active and future) with change
orders. Under this scenario, the required change order funding
would be in the range of $14 million which is $6 million less than
currently projected.
The PMT change order projection is conservative since:
·
It is
based on 6% change orders whereas current performance is in the 2 to
3% range It is based on 6% of all remaining funds whereas only a
portion of the remaining funds is anticipated to go to outside
contractors where change orders will be incurred.
Credits
– The credit projection was based on 4% of all remaining work in
December 2006 and resulted in a $20 million credit projection. If
this analysis is conducted for only contract work (total active and
future contract value) the credit projection is reduced to $13
million. Since October 2006 approximately $0.9 million in credits
have been processed. Significant credits are anticipated as
additional projects are completed and closed out. In October 2007,
two projects were in the closeout/final change order process with
$1.0 million and $0.8 million. These credit change orders will be
presented to the City Commission in November. With the credits
processed to date and 4% of the remaining active and future
contracts as potential credits; the PMT believes that the proposed
total $20 million total credit projection is still valid.
Summary – The current
contingency management evaluation shows that up to $20 million in
planned projects may need to be deferred to fund priority utility
needs. Based on the information presented above, the variance from
the current contingency projection can be summarized as follows:
Potential changes:
Remaining bid risk +$10 million
Change orders -$6 million
Credits +$7 million
Net impact $11 million
As shown above, the
net impact under a worst case scenario is that an additional $11 to
$17 million could be required. This estimate is much less than the
$27 to $79 million projected in the Audit Report. These are
extremely conservative estimates and there are several areas, such
as claims (planned at $5 million), where funding may not be required
resulting in additional funding availability.
If additional funds
are needed, options are:
·
Utility rates can be increased to cover the increased construction
costs; or
·
Projects can be deferred or scopes reduced to manage within the
current budget
The PMT’s current
strategy is to manage within the total program budget. Costs
associated with general construction cost increases, change orders,
and additional project scope will be funded using the remaining
contingency fund, as well as with funds from project scope reduction
and project deletion/deferral.
ES -4 – Projects
are not defined and tracked by the way the work is being contracted
and managed.
PCS general
practice for project and task numbering is as recommended in the
audit report. However, there are cases where the desired project
number has already been used for another project. In these cases,
deviations from the general project numbering practice have been
required and the system contains a general flag alerting the viewer
to that exception. Despite the importance of the numbering
convention, the program users have been trained to reference and
query the projects by name.
The PCS system has
the capability to link the projects and is routinely used to produce
reports that link the tasks. As an example, the Work Package report
links tasks from the various water and sewer components into a
summary for each project. Additionally, the system has been, and is
currently, used to track contract data and is able to produce
various standard reports as well as customized reports at any level.
Several example reports are provided in Appendix B.
ES-5 – Work being
performed for multiple projects, but contracted within one contract,
should be linked within PCS.
As noted in ES-4
above, the PCS system has the capability to link the projects and is
routinely used to produce reports that link the tasks. As an
example, the Work Package report links tasks from the various water
and sewer components into a summary for each project. Additionally,
the system has been, and is currently, used to track contract data
and is able to produce various standard reports as well as
customized reports at any level. Several example reports are
provided in Appendix B.
ES-6 – Program
reporting can be enhanced to better reflect project status and
performance measurements.
The PMT will
continue to respond to requests by internal and external
stakeholders to enhance reporting. Reports are currently focused on
performance metrics to facilitate review of program performance.
Continued tracking of construction starts, dollars expended,
projects completed and sewer certifications achieved continues to be
an appropriate measure of performance. Additional enhancements to
the reports have been implemented including: expansion of the goals,
activities, and issues section to reflect prior period performance;
graphical representations of data; fund source tracking; contingency
fund reporting; sewer connection tracking data; and contract
information.
ES-7 – The Change
Control Board review process should be strengthened to include
greater review of the cost impacts to the Program.
The list of
proposed contingency fund needs will be provided at the CCB such
that if a project withdrawal from the contingency fund is above that
in the projected list, a flag will be raised by the project controls
staff so that the project specific impact is immediately identified.
This new procedure will provide greater review of potential cost
impacts under current CCB procedures.
There is a keen
awareness of the cost impacts of proposed changes. Under the
current practice, each project that needs a budget increase is
scrutinized by the Change Control Board. The CCB considers issues
such as: the true cost of an individual project is largely
market-driven (i.e., award price is based on
competitively-established low bid proposal); and scope reduction is
often not feasible (e.g., design is needs-driven and in conformance
with typical municipal utility infrastructure standards).
Other improvements
to the CCB process that were implemented as a result of the
preliminary audit feedback have included presentation guidelines,
improved agendas, and improved decision tracking.
CCB Presentation
Guidelines
– The Change Control Board has proven to be an effective forum for
managing changes on the program. The team will continue to work
diligently to ensure that the information provided to the CCB is as
complete and as informative as possible. The PMT has developed
presentation guidelines, which will provide better consistency among
the CCB presenters. In addition, these guidelines will be used by
the lead team to determine that impacts have been appropriately
presented and discussed. There are multiple levels of presentation
of change order issues to the CCB, such as Heads Up, Action Item,
Draft Change Order and Final Change Order. Each type of
presentation demands differing levels of detail/background knowledge
of the presenter.
Improved Agendas
- At the time of the performance review, the CCB agenda consisted of
a list of people that would be presenting items at the CCB meeting.
This list is sent via e-mail to the CCB participants the day prior
to the meeting. Based on preliminary feedback from the review team,
the agenda was revised to include a listing of the items each person
is presenting. Distribution of the agenda the day prior to the
meeting continues.
Improved Tracking
System -
Based on preliminary feedback from the review team, significant
improvements to the CCB have been implemented. The agenda listing
topics to be discussed is distributed prior to the meeting, a list
of attendees is recorded, and a formal tracking system has been
developed to track items presented and decisions made. Previously,
the decisions were tracked on the paper record produced for the
meeting, which was difficult to search. The new electronic log
system allows for searches of the CCB items by presenter, project or
date. In addition, the presenters have been provided with
guidelines for presenting information, which will allow the
presenters to be better prepared and to provide consistency among
the presentations.
ES-8 – The City
should consider including a Change Order Allowance in construction
contracts.
The idea of
increasing approval thresholds for change orders is currently under
consideration (low threshold of $10,000 inhibits the ability to
react timely to construction issues, and to pay timely for delays
and other unforeseen construction impacts). Change order allowances
cannot be used to preempt approval requirements established under
the City’s Code of Ordinances.
Contract and
Performance Related Observations
ES-9 – The City’s
Program Manager may be overextended in the WaterWorks 2011 Program.
Staff will explore
options for expanding the formal responsibilities of the Engineering
Design Manager position vacated by Maurice Tobon to possibly include
deputy program management responsibilities in support of the City’s
program manager. Immediately prior to SBC’s engagement, Maurice
Tobon, who had been serving in the capacity of a deputy program
manager in many ways, was promoted out of the WaterWorks 2011
program. Tim Ashmore, Engineering Design Manager in the
WaterWorks 2011 program has assisted at the program level on
occasion since that time.
ES-10 – There
should not be direct or indirect oversight of City personnel by
CH2M HILL.
Direct and indirect
oversight of City personnel by CH2M HILL will be eliminated to the
extent possible by increasing the number of construction projects
being managed by City Engineering Design Managers; by reassigning
City Engineering Inspectors to those projects being managed by City
Engineering Design Managers; and by having the City Engineering
Design Manager responsible for the City in-house design team perform
program-level design manager duties. There are currently two City
Engineering Design Managers that perform the duties of Construction
Manager. Their role as Construction Manager will be increased; and
City Engineering Inspectors will be reassigned to projects being
managed by them.
There is currently
one City Engineering Design Manager responsible for management of
the City in-house design team. That Design Manager will take-on the
additional duties associated with schedule and budget maintenance
and reporting at the program level – thereby eliminating CH2M HILL
design manager involvement.
Financial Framework
Observations
ES-11: There area
areas for enhancements to the Financial model which include but are
not limited to the following:
·
Training City staff to understand and utilize the Financial Model to
improve and enhance internal controls.
·
Potentially streamline water and sewer projection methodologies.
·
Potentially consolidate current external Excel files into one model
in order to dynamically link all relevant information.
·
Potentially develop one or a few schedules which consolidate all
assumptions.
City Financial
Model Operations/Staff Training - The financial modeler will work with City staff so that they have a
higher level of understanding of the model and can provide input on
assumptions. As it currently exists, the financial model is complex
and would require a significant effort for the City to assume the
modeling role. As an example, the model uses many sources for the
data used to generate the forecast which include, but are not
limited, to the following: City FAMIS accounting system reports, the
annual financial statements, budgeting documents and analysis,
operating data, utility billing and collections, various engineering
studies and forecasts, financial and rate studies, and comprehensive
plan.
A detailed,
complex financial model may not be required if it is only used for
budgeting purposes (i.e., once the complex CIP is complete). The
City could consider development of a simpler management tool to
assist in estimating the longer term budget impacts of annual
capital improvements in the future.
The City may want
to use the current model only for external financing purposes and
for evaluating the impact of alternative courses of action. The City
has used the model for handling “what if” questions numerous times
since the inception of the WaterWorks program.
Streamline
Projection Methodologies
- There are various sources for the data, most are in hard copy
format, and many require analysis to make final determinations on
the proper data to use within the model structure. Further
streamlining this process could be done but would not provide a
significant benefit.
Consolidating Excel
Schedules
- The model currently links many external Excel files for direct
input into the model. Opportunities exist to provide additional
links including those to revenue and billing reports that are
expected to be developed by the City in the near future. These
additional links and consolidation can be implemented in the next
financial model update.
Consolidating
Assumption Schedules
- The model currently includes a schedule that outlines all the
major assumptions.
SBC also suggested
a utility billing analysis be performed on an annual basis. The City
is currently proceeding to create utility billing reports that will
allow a utility billing analysis to be performed on demand and has
contracted to purchase a new utility billing system that has
extensive management reporting capabilities.
Remaining
Observations
Responses to the
remaining audit report observations are summarized in Exhibit 1. A
summary of significant observations and responses from Exhibit 1 is
provided below:
Invoice Review
- The invoice review checklist will be modified to include percent
complete and common lump sum contract items (such as mobilization).
The invoice review checklist was designed at the beginning of the
program as a generic guide with 21 items and will be further
enhanced through these additions. In addition, staff have started
utilizing a mobilization payment eligibility calculation in the
electronic worksheet copies of the contractor pay applications.
Prompt Payment
- The program prompt payment policy is based on 19 business days and
a revised analysis of the payment process based on business days
(not calendar days) shows that 92% of program invoices were
processed in this timeframe. The PMT continues to focus on payment
efficiency to retain a strong working relationship with the
contractors as well as to meet ongoing program performance measures.
The team has instituted a number of processes and procedures
including prompt payment invoice reviews and the use of uniquely
colored cover folders for each pay application in order to
distinguish them from other documents on team member's desks.
PCS Enhancements
- PCS will be re-programmed to provide a flag to identify a cost
greater than budget at the moment of entry as an additional control
measure. However, appropriate controls are currently in place to
monitor this situation. Under current practice, when expenditures
exceed budget, the task is identified in the Cost Performance
Report, which is distributed in the Monthly Schedule Meeting. Any
task with cost greater than budget is flagged for the design manager
or construction manager to update the budget. A copy of the Cost
Performance Report is provided in Appendix 2.
Conclusions
The Audit Report
findings indicate that CH2M HILL has implemented solid program
management practices for the WaterWorks program. Several of
the observations have been implemented by the team to further
enhance to program’s operations, practices, processes, and
procedures.
Contingency Fund
–
Current funding is adequate and is being managed to prioritize
utility needs.
As shown in the
analysis included in this response, the PMT still feels that the
current projection is adequate. Under a worst case scenario, an
additional $11 to $17 million could be required. This estimate is
much less than the $27 to $79 million projected in the Audit Report.
These are extremely conservative estimates and there are several
areas, such as claims (planned at $5 million), where funding may not
be required resulting in additional funding availability.
If additional funds
are needed, the Commission has a choice:
·
Utility rates can be increased to cover the increased construction
costs; or
·
Projects can be deferred or scopes reduced to manage within the
current budget
The PMT’s current
strategy is to manage within the total program budget. Costs
associated with general construction cost increases, change orders,
and additional project scope will be funded using the remaining
contingency fund, as well as with funds from project scope reduction
and project deletion/deferral.
Program Control
System –
PCS is a viable tracking system and from a technological
perspective, has the capability and flexibility needed to
successfully track costs, schedule, and changes for the
WaterWorks program.
Change Control
Board –
The CCB has been strengthened to provide a greater awareness of
change impacts, improved presentations, and improved tracking of the
results.
Summary
The observations
provided in the Audit Report indicate that the program areas
selected for review:
1.
contain sufficient management controls
2.
produce reliable and timely financial and operating
results
3.
are
materially compliant with applicable laws, regulations and contracts
4.
effectively contribute to the successful execution of the
Program
The WaterWorks
2011 Program Management Team was encouraged that the SBC Review
Team found solid program management practices in place. The PMT
also recognizes that the observations provide an opportunity to
enhance the program’s operations, practices, processes, and
procedures. Several of the observations provided to the team during
preliminary feedback discussions are excellent suggestions which
have already been implemented by the team including reporting
improvements and Change Control Board process improvements.
Implementing these enhancements will only serve to further
strengthen the solid program management practices already in use on
the WaterWorks program.